Project SummaryLa Grande Construction Dam |
1. Project ID
- Name
La Grande Construction Dam
- Region
North Western
- State
WA
- Location
Eatonsville
- Date of this update
6/22/00
Habitat Restoration/Protection Wetlands
River systems
Beaches/Dunes
Offshore areas
Mangroves
Assisting Species at Risk Pollution Mitigation Non-Point Source Pollution
Other (describe)
3. Project description (100 words or less)
The La Grande construction dam is located near Eatonsville, WA, about 15 to 20 miles west of Mount Ranier National Forest. The dam was built around the 1940's to block water so that a dam powerhouse could be built downstream. The dam is located about midway between the reservoir and the powerhouse. An underground aqueduct runs for over a mile from the La Grande Dam reservoir to the powerhouse. There isn't much flow over the dam except where there is a release from the La Grande Dam. Tacoma Public Utilities would like at least half of the construction dam removed in order to facilitate fish passage.
4. Goals/Benefits (quantify where possible using measures of success list) Was a cost-benefit study conducted for this project? yes/no If yes, provide a summary of findings.
Removal of the construction dam would allow for better fish passage.
5. Partners (include each participant's responsibilities - funding, permitting, etc.)
| Federal |
Lead: |
| Non Federal: | Non Federal: State government: Seattle District Local government Private industry: Tacoma Public Utilities Public interest groups Educational Facility Other |
6. Funding/Contributions (organization and amount)
Cash Federal Non Federal State government Local government Private industry Public interest groups Total In-Kind Services (hours, equipment, or other forms of assistance and estimated dollar value) Volunteers (number of people and hours, and estimated dollar value)
7. Legislative authorities used by each participant
8. Value added by Coastal America Partnership including Government Performance and Results Act (GPRA) goals achieved through this collaboration (500 words or less)
9. Project Status
10.Contacts
|
Glen Reed 202-764-3576 Glen.Reid@nws02.usace.army.mil |
|
11. Any additional information/comments