Project SummaryFlock Process (Winnipauk) Dam |
Name Flock Process (Winnipauk) Dam Region North East State CT Location Norwalk Date of this update 1/25/02
Habitat Restoration/Protection Wetlands
River systems
Beaches/Dunes
Offshore areas
Mangroves
Assisting Species at Risk Pollution Mitigation Non-Point Source Pollution
Other (describe)
A 22 feet high masonry dam is a barrier to a possible 17 miles of riparian stream capable of supporting cold water and anadromous fisheries. The Norwalk River Watershed Initiative, CT DEP is looking to remove the dam or to remove the upper portion of the dam and construct a fish passage. Wetland Mapping and the preliminary engineering have been completed, the project could take between $350,000 and $1 million.
---
Lead:
Other:
State government: Norwalk River Watershed Inititive, CT DEP
Local government:
Private industry:
Public interest groups:
Educational Facility:
Other partnerships:
Federal Non Federal State government Local government Private industry Public interest groups Total
---
---
---
---
Initiation date Completion date Current stage
Chris Malik
CTDEP - LSIP
79 Elm St., Hartford, CT 06106-5127
(860) 424-3959
Email: christopher.malik@po.state.ct.us
---
|
Federal Partners | Innovative Readiness Training (IRT) | Internal Site |
|
|